What will it take to deliver the value?

A project usually involves more than technical delivery. The business needs to prepare, employees need to learn new workflows, and someone must communicate, provide support, and follow up.

The project size model brings this together in size units (SE). You also retain a separate view of actual hours and spending.

Three components of project size

  • Base estimate: Work and purchases you can describe and estimate now.
  • Identified risks: Additional effort if specific events occur.
  • Residual uncertainty: A justified reserve for other unresolved factors.

Known work is not certain work. A reserve must not cover effort already included in the base estimate or an identified risk.

One consistent unit across projects

In EnableAI’s example profile, 1 SE = 37.5 internal hours, equivalent to approximately $3,400 in reference resources at 2026 prices. This is a fixed resource weight, not a billing rate. For example, 75 internal hours plus approximately $3,400 in purchases produce 3 SE before risk, using unrounded reference values.

Include participants’ time: training 40 employees for two hours takes 80 staff hours before preparation and instruction. This applies to AI projects, IT projects, and other organizational changes.

Learn to make estimates verifiable

In the half-day workshop on SE and prioritization you work with activities, purchases, risks, and follow-up. Half-day workshop 1 on VP establishes the value side of the assessment. Each workshop lasts four hours, including a break.

This is a brief introduction. Applying the model requires a clear scope, documented assumptions, and an assessment of schedule, capacity, and finances. Read the instructor guide to SE and see the combined models.

Methodological background

The approach to work breakdown and follow-up draws on GAO. SE, the reference rate, and the reserve formula are EnableAI’s choices. They are not an industry standard or a guarantee of budget accuracy.